Lower Way in Thatcham has been shut since 11 September for sewer repairs. The council says there is no reopening date yet; Thames Water aims for Christmas.
There is still no confirmed date for Lower Way in Thatcham to reopen. The road has been shut since 11 September while Thames Water repairs the sewer network.
West Berkshire Council said on Tuesday 10 November that the work “has proved more complex than initially anticipated”. Specialist materials are now needed to finish the repairs.
Thames Water is working towards reopening the road before Christmas. The council said that “cannot be guaranteed” and depends on progress and on getting the materials.
(West Berkshire Council, 10 November 2026)
What the council said
The council’s update makes these points:
- a temporary overland sewer pipe has been put in to keep the wastewater network running while the longer-term repairs are done
- that pipe is also reducing the need for wastewater tankers in the area
- the council asked whether the closure could be made shorter in length, and Thames Water said not without compromising safe delivery of the repairs, or risking more delays and disruption on the A4
- Thames Water has committed to weekly progress updates, which the council says it will share with residents
The two ward councillors for Thatcham West are Jeff Brooks, the council leader, and Justin Pemberton. In a joint statement they said: “We know how frustrating the continued closure of Lower Way is for people living and working in Thatcham, particularly given how long the disruption has continued.”
They added that “there is still uncertainty around that timescale”, and that the council would keep seeking “clear and regular updates”.
The permit has been extended twice
The street works register shows how the expected end has moved. Thames Water started the job at 4pm on Friday 11 September, as urgent works with a road closure.
- its first permit ran to 22 October
- on 15 October an alteration moved the end to 15 November
- on 5 November a second alteration moved it to 20 December
(Department for Transport street works register, works reference MU074LOWERWAY, via StreetGuide)
That takes the permitted closure from 41 days to 100. By today, 11 November, the road has been shut for 61 days.
The register describes the job as utility asset works affecting the footway, carriageway and verge. A permit end date is the latest the works may run, not a promise of when the road will reopen. The road could reopen earlier, or the permit could be extended again.
What it means for you
- Lower Way stays closed for now. Do not plan on it reopening before the second half of December.
- Expect the A4 through Thatcham to carry the traffic. The council’s own reason for not shortening the closure was the risk to the A4.
- Watch for the weekly updates. The council says it will pass on Thames Water’s progress reports as they arrive. We will add them here.
- Problems with the works go to Thames Water first, quoting reference MU074LOWERWAY, then to West Berkshire Council, which authorised the permit.
Our Newbury roadworks page carries this and every other closure around Newbury and Thatcham, checked against the register and National Highways each week.
What we could not confirm
The council’s update does not say which stretch of Lower Way is closed or what diversion is signed. Thames Water has not published a project page for the job that we could find.